Whatever It Takes
Location: Whatever It Takes, Clapham, SW11
Type: Commercial design and build
Client: Whatever It Takes Retail
Project Length: 6 weeks
Project Cost: £70,000
Project Brief: Store fit out
Challenges: The works needed to be carried out within a tight timeframe to match the store’s opening date. Nine weeks’ work was carried out in just six weeks.
Work Carried Out:
- new electrics installed above finished ceiling and under floor
- service and re-spray of air-conditioning cassette
- new bespoke lighting on walls and ceilings
- constructing new walls and changing room, including new decoration
- store room and back office fit-out, including t-point design, supply and fit
- re-surfacing the floor and installing new bespoke gym matting
- new vinyl flooring to the back office, store room and WC
- Refurbishing WC, including new bespoke joinery to conceal distribution board and electric meters